TR-6: Repair or Retrofit Timber Piles With an Underwater Curing Epoxy
TR-7: Replacing Damaged Pile With New Timber Pile Under Timber Pier Deck

Maintenance of Waterfront Facilities - index
Page Navigation
  121    122    123    124    125  126  127    128    129    130    131  
UFC 4-150-07
19 June 2001
Figure 6-6 Repair by Oriented Fiber Wraps
15-cm Overlap
15-cm Overlap
Approx. 60- cm
15-cm Overlap
6-18