UFC 3-430-07
24 July 2003
including Change 1, Jan 2004 and Change 2, March 2005
CHAPTER 11
MISHAP OR PROPERTY DAMAGE REPORTING
11-1
REPORTING REQUIREMENTS. OPNAVINST 5102.1C, Mishap
Investigation and Reporting, requires that incidents which satisfy the following criteria be
reported to the activity Safety Office for investigation and reporting to the Naval Safety
Center:
Damage to property involving a repair or replacement cost equal to or
exceeding ,000.
or
Any incident involving a lost time employee mishap.
This instruction also encourages reporting of incidents where serious injury to Navy
personnel was possible or if there was a "lesson to be learned."
11-2
INFORMATION COPIES. A copy of the required report for all incidents
relating to the construction, repair, operation and maintenance of the boilers and unfired
pressure vessels covered by this UFC must be forwarded to the cognizant NAVFAC
Senior Boiler Inspector for information.
32