MIL-HDBK-1165
APPENDIX D (Continued)
3.
EFD - Engineering Field Activity:
a. Performs technical evaluations on
submitted and programmed project packages based on technical
assumptions, water and cost savings, and construction cost
estimates.
b. Provides assistance in identifying,
developing, and auditing FEMP and ECIP projects.
c. Executes the engineering contract efforts
requested by the activity.
4.
Claimant:
a. Endorses EFD validated project packages
depending on funding requirements, future use of the facility,
and concurrence with claimant policies and directives.
b. Provides assistance to installations by
using O&M standards, management guidance, and engineering
expertise to identify and implement energy and water conservation
efforts.
5.
NFESC - Naval Facilities Engineering Service
Center:
a. Reviews project submittals for
consistency in technical and life cycle cost suitability and
prioritizes them by SIR and payback.
b. Enters project data into a computer
database and maintains the database for tracking and reporting of
projects.
c. Provides technical and engineering
services as well as information resource management in support of
the Navy's energy and water conservation programs.
6.
Energy Projects Team:
a. Made up of energy personnel from the
EFD's, PWC's, NFESC and NAVFACENGCOM.
107