UFC 3-560-01
6 December 2006
Including change 1, 7 December 2006
2-6.3
Interpretation.................................................................................
2-5
2-6.4
Violations ......................................................................................
2-5
CHAPTER 3 PRE-SITE SAFETY MANAGEMENT
Paragraph
3-1
WORK LOCATION SAFETY REQUIREMENTS ..........................
3-1
3-1.1
Working Near Energized Circuits..................................................
3-1
3-1.2
Work Location ...............................................................................
3-4
3-2
PUBLIC SAFETY ..........................................................................
3-4
3-2.1
Warning Devices...........................................................................
3-4
3-2.2
Flagmen ........................................................................................
3-4
3-2.3
Excavations ..................................................................................
3-5
3-3
NUMBER OF WORKERS REQUIRED.........................................
3-6
3-4
VERIFYING SYSTEM AND EQUIPMENT PROVISIONS ............
3-8
CHAPTER 4 PERSONAL PROTECTIVE EQUIPMENT
Paragraph
4-1
INTRODUCTION ..........................................................................
4-1
4-2
INSPECTION OF APPAREL, TOOLS, AND MATERIALS
HANDLING EQUIPMENT ........................................................
4-1
4-3
PERSONAL PROTECTIVE APPAREL.........................................
4-1
4-3.1
Applicable Documents ..................................................................
4-1
4-3.2
General Clothing Considerations ..................................................
4-2
4-4
PERSONAL PROTECTIVE EQUIPMENT FOR ARC
FLASH PROTECTION.............................................................
4-2
4-5
AIR FORCE PPE REQUIREMENTS FOR HIGH-VOLTAGE
OVERHEAD LINE WORK AT 69 KV (NOMINAL) OR LESS..
4-15
4-5.1
Background...................................................................................
4-15
4-5.2
Overhead Lines Above 35 kV Hot Stick Distance Less
Than 10 Feet ...........................................................................
4-16
4-5.3
Overhead Lines Above 35 kV Hot Stick Distance More
Than 10 Feet ...........................................................................
4-16
4-5.4
Overhead Lines ≤35 kV Hot Stick Distance More Than 8 Feet .
4-17
4-5.5
Overhead Lines ≤35 kV Hot Stick Distance Less Than 8 Feet ..
4-18
4-6
CLOTHING PROHIBITIONS ........................................................
4-19
4-7
SKIN PROTECTION .....................................................................
4-19
4-8
POLE/TREE CLIMBING AND FALL PROTECTION ....................
4-20
4-8.1
Personal Protective Equipment ....................................................
4-20
4-8.2
Climbing Personal Protective Equipment .....................................
4-20
4-8.3
Fall Protection Personal Protective Equipment ............................
4-20
CHAPTER 5 WORK AREA PROTECTIVE EQUIPMENT AND TOOLS
Paragraph
5-1
INTRODUCTION ..........................................................................
5-1
5-2
RUBBER PROTECTIVE EQUIPMENT ........................................
5-1
5-2.1
Job Requirements.........................................................................
5-1
5-2.2
Use of Rubber Protective Equipment ...........................................
5-1
5-2.3
Use of Rubber Gloves ..................................................................
5-2
5-2.4
Use of Rubber Sleeves .................................................................
5-3
5-2.5
Care and Inspection......................................................................
5-3
ii