SCHEMATIC DESIGN PHASE
10-5.1
During schematic design, system solutions for the project issues (problems)
identified during programming will be generated. The key product for this phase will be
outlined technical specifications and one-line riser diagrams. The schematic design
documents can be used to provide the first cost estimate not based on concepts.
10-5.2
Initial panel board schedules should be started to indicate power sources for
ESS equipment. Any new needs for power panels should be identified by electrical
power one-line diagrams.
10-6
DESIGN DEVELOPMENT PHASE
10-6.1
During the design development phase, project plans and specifications will be
completed. Drawings should include the following:
10-6.1.1 Legends and abbreviations
10-6.1.2 Site plans
10-6.1.3 Floor plans
10-6.1.4 Riser diagrams
10-6.1.5 Mounting details
10-6.1.6 Door hardware schedule (may be on architectural plans)
10-6.1.7 Sequence of construction when applicable
10-6.1.8 Site and floor plans will include power panel locations, security panels,
consoles, sensors, cameras, card readers, power circuits, and other related equipment.
Riser diagrams should include all devices (including location and zoning requirements),
cabling, power connections, grounding, and required system interfaces.
10-6.1.9 The system designer should have owner feedback on any changes to devices
upon completion of the design development review meeting.
10-7
BIDDING
10-7.1
Installers and System Integrators. Installers and integrators must be
experienced in the installation, tuning, and programming of ESS. Require a minimum of
three years of documented experience for the types of systems the project includes.