MIL-HDBK-1022A
f) Externally coat unpainted and unwrapped lines
exposed to the weather with a corrosion-preventive compound.
13.3.2.1
Pipeline Equipment
a) Remove, clean, coat inside and outside with a
light oil, and reinstall strainers.
b) Remove, clean, treat with corrosion-preventive
compound, and store meters in a dry place.
c) Keep gaskets tight to prevent dirt and water from
entering.
d) Remove, clean, grease, and store hydraulically
operated diaphragm control valves in a dry place.
e) Paint exterior or treat with a corrosion-
preventive compound and leave all other valves, such as plug
valves and check valves in place.
f) Lubricate plug valves and leave in an open
position.
g) Remove, tag, date, and store hoses in dry
storage.
13.3.2.2
Fueling Pits
a) Inspect, tag, and secure fueling pits.
b) Make provisions for pumping pits dry.
13.4
FACILITIES
13.4.1
a) Make arrangements to retain the minimum amount of
maintenance equipment.
b) Check and label all keys to all doors, gates,
hatches, and other moving items.