UFC 3-460-03
21 JANUARY 2003
12.3. TES. The LFM TES, working with contract management and the contracting officer, provides
overall coordination of the project. TES responsibilities are:
12.3.1. Advise the contractor, through pre-work meetings with the contracting office, of known
potential hazards within the tank and the surrounding area.
12.3.2. Provide contract surveillance in all technical matters pertaining to the work. Immediately
advise the contract inspector of noncompliance with safety or environmental requirements.
12.3.3. Inspect the contractor's equipment to ensure it is in working order and meets all applicable
regulations.
12.4. Air Force Forms Prescribed. AF Form 172, Tank Inspection Summary.
129