UFC 4-171-05
1 January 2005
with change 25 October 2006
APPenDIX C
OMAR-FUnDeD IteMs
C-1
General
C-1.1
||content||
\ OMAR funding for furniture and collateral equipment associated with newly
constructed AR training facilities must be identified well in advance of project execution
for budgetary purposes. Physical fitness equipment will be funded at the same time as
furniture, as Government furnished/ Government-installed (GFGI) equipment./1/
C-1.2
||content||
\ MCAR funding in general applies to items permanently attached to the
structure which cannot be relocated to other facilities for easy reuse. Items that can be
moved and reused with relative ease are considered collateral equipment and, as such,
will be OMAR -funded. OMAR- funding associated with Contractor Furnished /
Contractor Installed (CFCI) collateral equipment is required at the time of award of the
construction contracts. The bid documents (specifications and drawings) must clearly
define what OMAR-funded collateral equipment is. The bid form must have an OMAR
Collateral Equipment line item as part of the base bid. The bid form shall also narratively
define what constitutes OMAR Collateral Equipment. The furniture and physical
readiness equipment will be funded approximately six months prior to beneficial
occupancy date (BOD) as Government Furnished / Government Installed (GFGI) items.
/1/
C-2
CFCI OMAR - Funded Items (Funded at time of construction award)
C-2.1 Kitchen Equipment
Tray and silver dispenser
Cup and glass dispenser
\ Juice dispenser /2/
Silver soak pan
Coffee urn
Mobile hot food well
||content||
\ Mobile cold food well
Warming cabinet
Refrigerator
Freezer
Table Food Prep w/ Pot Rack
Can opener
Slicer
Worktable, mobile
Mixer
Mixer stand
Mobile Rack
Kitchen Shelving
Double tray bussing racks /1/
161