Project Name
Project No. ___________
UFC 4-214-02, TEMF, 24 July 03
construction; performance by the contractor's own employees of design work, land surveys and other
engineering or technical specialist services required by the contract; supplies to directly support the
aforementioned work to be accomplished by the contractor's own employees; and the contractor's own
job overhead costs. Contractor markups for profit, general and administrative overhead, bonds, or other
indirect costs on "self-performed" or subcontracted work are not "self-performed work" and are to be
excluded from "total cost of the contract" for calculation purposes. Rental of plant or equipment for
operation by subcontractors is not "self-performed work" but shall be included in the "total cost of the
contract" for calculation purposes . Cost of materials to be incorporated into the work and supplies to
support other than construction by the contractor's own employees are excluded from the above
definition. Do not include these costs in the calculation.
XX.1.3 "Total cost of the contract" means the total direct (variable, fixed, one-time and semi-variable)
costs to the contractor, including jobsite overhead costs but excluding the cost of any materials to be
incorporated into the work, to construct the project. It generally includes the cost of all self-performed
work, as defined above, and all supplies and subcontract costs. The cost of subcontractor furnished
materials will be excluded only to the extent that they can be segregated and identified in the
subcontractors' proposals.
XX.1.4 "Percent of self-performed work" is calculated by dividing the above defined cost of "self-
performed work" by the "total cost of the contract" and multiplying the result by 100%."
COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
Adapt this clause and Specification Section 01320, Project Schedule, as necessary to meet your
requirements. You may state separate completion times for the design and the construction; however,
this is discouraged. The recommendation is to state one completion time inclusive of both design and
construction. If you allow the offerors to propose the contract duration period, add wording to cover
acceptance of the selected offeror's proposed performance period not to exceed a prescribed maximum
period.
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (Apr 1984)
(a) The Contractor shall be required to (1) commence work under this contract within 10 calendar days
after the date the Contractor receives the notice to proceed, (2) prosecute the work diligently, and (3)
design and construct the entire work.......<--If the performance period is to be proposed by the
offerors, use wording to this effect: "....ready for use not later than the proposed performance
period after receipt of the contract notice to proceed. The maximum proposed performance
period cannot exceed _____calendar days after receipt of the notice to proceed."> The times stated
for completion shall include final cleanup of the premises.
(b) Provisions stipulated for conducting test on heating and air conditioning systems and planting and
maintenance of grass are excluded from the completion time stated above.
(End of Clause)
GOVERNMENT RIGHTS (UNLIMITED).
Use this DFARS clause in all design-build contracts, except those using the DFARS clause: DRAWINGS
AND OTHER DATA TO BECOME PROPERTY OF THE GOVERNMENT.
The clause grants the
Government non-exclusive rights to use the design on other projects.
00700 - 9