MIL-HDBK-1191
milestones in Figure 2-1. The Design Agent manages design in accordance
with established policies and procedures unless otherwise established in
coordination with the user and TMA/DMFO during initial project acquisition
strategy planning. Separate design authorization memoranda are normally
issued for A-E Selection, Concept Design, and Final Design. However,
separate or combined DA's may be issued for design-build projects. The
Design Agents shall not pursue any level of design beyond that authorized in
writing by TMA/RM.
Figure 2-1
DoD MEDICAL MILITARY CONSTRUCTION TIMETABLE
FOR PLANNING, BUDGETING, AND EXECUTION
OF A "TYPICAL" MILCON" PROJECT IN THE FY XX PROGRAM
THIS IS A MINIMUM TIMETABLE WHICH DOES NOT PRECLUDE EARLIER
DESIGN STARTS FOR OCONUS, LARGE, OR COMPLEX PROJECTS OR TO MEET ALTERNATIVE
EXECUTION STRATEGIES (E.G., DESIGN-BUILD, etc) DEVELOPED JOINTLY BY TMA, THE
AGENT, AND THE SERVICE--CRITICAL MILESTONES ARE IN BOLDFACE
ACTIVITY
FY 02
FY 03
FY 04
Begin FYXX Planning Year
FEB 98
FEB 99
FEB 00
Begin FYXX EA Efforts (Services)
JUL 98
JUL 99
JUL 00
FYXX EA Efforts Completed (Services) and Validated (DMFO)
APR 99
APR 00
APR 01
Preliminary Scope Available (Services)
Determine Execution Strategy (Services/Design Agent/DMFO)
. Submit Project Book to TMA
. Final PFD and DD Form 1391 validated by TMA
MAY 00
MAY 01
MAY 99
Release Design Authorization (TMA)
2807 Action (TMA)
Issue 35% Design Authorization (TMA)
OCT 99
OCT 00
OCT 01
Best Concept Design Cost Estimate to TMA (Design Agent)
JUL 00
JUL 01
JUL 02
35% Design Submission to TMA (Design Agent)
AUG 00
JUL 01
JUL02
Scope and PA Approval and 35% Design Certified (TMA)
SEP 00
AUG 01
AUG 02
FYXX Budget Submitted to OSD(Comp) (TMA)
SEP 00
SEP 01
SEP 02
Issue Final Design Authorization (TMA)
OCT 00
OCT 01
OCT 02
FYXX MILCON Program to Congress (DOD)
JAN 01
JAN 02
JAN 03
Ready to Advertise (Design Agent)
SEP 01
SEP02
SEP03
FYXX Funds Available (TMA)
Nov 01
NOV 02 NOV 03
2-2