UFC 4-740-02
26 September 2006
Conditioning (HVAC) Control Systems. Comply with AT requirements in the design of
the HVAC system (see Paragraph 3-8).
Do not locate HVAC equipment above the gymnasium due to the risk of a leak causing
water damage.
3-5.3
Fire Protection.
Design fire protection and life safety to comply with UFC 3-600-01, Fire Protection
Engineering For Facilities.
3-5.4
Electrical.
Provide electric service and distribution equipment, wiring receptacles and grounding,
interior and exterior lighting and control, emergency lighting, telephone, communication
systems, fire alarm, other health and safety alarms, and intrusion systems in
accordance with NFPA 70, National Electrical Code; UFC 3-520-01, Interior Electrical
Systems; and the latest Installation design requirements. See the latest edition of
Electric Current Abroad, U.S. Department of Commerce, to determine voltages and
cycles in overseas locations. Service grounding system and all wiring methods must
meet the current NFPA 70 requirements. All service equipment must be Underwriters
Laboratories (UL) listed. Alternately, published proof from an approved independent
testing laboratory may be provided.
3-5.4.1
Lighting.
Provide lighting and control systems throughout the facility in accordance with UFC 3-
530-01, Interior and Exterior Lighting and Controls. Pay particular attention to issues
such as glare, heat generation, and impact protection for the fixtures in Fitness Facility
activity spaces.
3-5.4.2
Telephone and data outlets may be independent of each other or combined into a single
junction box. Also consider wireless audio, video, and data installations for Fitness
Facilities to add flexibility. If the hard-wired connections can be combined into a single
junction box then the cover plate to that junction box must allow for multiple
connections. In some unique situations, the cable television (CATV)/internal video
connection can also be combined into a single junction box with the appropriate cover
plate. Identify the preference for individual or combined telephone/data/video outlets
with the following Service-specific contacts:
a. The Installation Manager for Army projects,
b. The project manager for Air Force projects, and
c. HQ Program Managers for Navy and Marine Corps projects.
3-4