UFC 3 -520-01
June 10, 2002
CHAPTER 2
PRELIMINARY AND DETAILED DESIGN ANALYSIS
2-1
PRELIMINARY DESIGN .
2-1.1
Principal Points of Contact.
2-1.1.1 Air Force. Contact the MAJCOM with additional support provided by the Air
Force Civil Engineer Support Agency (AFCESA) at www.afcesa .af.mil. The following
organizations also provide technical support:
Contact the Air Force Center for Environmental Excellence (AFCEE) at
www.afcee.brooks.af.mil for design guidance and support of medical facilities,
family housing and architectural design.
Contact the Power Conditioning and Continuation Interfacing Equipment (PCCIE)
Product Group at Hill Air Force Base (AFB) for assistance with power quality
design and operation issues. The PCCIE Materiel Group offers optimum
centralized processes in the areas of engineering/technical support, acquisition,
fielding, and sustainment of all power conditioning equipment, continuous
uninterrupted power equipment, power quality systems, and ancillary PCCIE
equipment. The web site is located at http://www.hill.af.mil/li/lip/lip.htm .
2-1.1.2 Army. Contact the US Army Corps of Engineers (USACE) at
http://www.usace.army.mil/inet/functions/cw/cecwe/.
2-1.1.3 Navy. Contact the Naval Facilities Engineering Command (NAVFAC) Criteria
Office at http://criteria.navfac.navy.mil/criteria.
2-1.2
Preliminary Design Guidance for Interior Electrical Systems. Review the
following documents for information regarding preliminary design considerations:
Engineering Regulation (ER) 1110-345-700, Design Analysis, Drawings, and
Specifications provides a checklist of electrical issues to consider early in the
design phase.
ER 1110-345-723, Systems Commissioning Procedures provides guidance
regarding the planning and review of procedures for the commissioning process,
which should be cons idered as early as possible in the design process.
Military Handbook (MIL-HDBK) 1004/1, Electrical Engineering Preliminary Design
Considerations provides detailed guidance regarding load estimation and
power source selection.
2-1