MIL-HDBK-1025/10
requirement correctly filled in for each specific ship's service and for each service period. SOP's
will be distributed to all personnel involved.
9.5.2.2 Specific Organization Requirements. The names of shore personnel and their
responsibilities will be listed. The name of the ship and the docking location will be given. The
ship's specific requirements as to the following will be noted.
a. Voltage of the estimated ampere load requirements including supershore electrical
power.
b. Number of ship-to-shore power cables required.
c. Type of cable terminations, in-line connections, jumpers, as required.
d. Identification of any interface problems.
e. Special paralleling requirements if any longer than 10 seconds for ship-to-shore
Note
Determine if there are any unusual job hazards. Identify the power cable
rigging device (boom trucks, cranes, fork lifts) and whether their location
requires structural approval by a facility engineer of their proposed
location. Verify that any construction work will not interfere with power
cable placing and rigging. Determine special safety provisions. (See
picture K.)
140