MIL-HDBK-1024/1
+)))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))))),
*
*
*
*
Air Passenger Terminal
*
*
*
*
Plumbing Requirements: G.P.M.
*
*
Water;
*
*
*
*
Cold
80
*
*
Hot
*
*
Recovery Rate (100 Degs. Rise)
42
*
*
Storage (Gal)
100
*
*
Fire Protection Requirements
*
*
Not Included
*
*
*
*
Heating Requirements (BTU/HR x 1000):
*
*
(Inside Design Temperature = 72 Degs. F)
*
*
Outside Design Temperature
-5 Degs. F
400
*
*
+5 Degs. F
350
*
*
+15 Degs. F
300
*
*
+25 Degs. F
250
*
*
*
*
*
*
Based on 91 Degs. D.B.
76 Degs. W.B. Outside Design
*
*
Conditions; Cooling Load
550
*
*
*
*
Heat rejected to conditioned spaces by energized test.
*
*
Equipment & parts under repair not included.
*
*
*
*
Electrical Requirements (KVA):
*
*
Lights;
*
*
Connected Load
9.0
*
*
Estimated Demand
7.0
*
*
*
*
Power;
*
*
Connected Load
16.0
*
*
Estimated Demand
13.0
*
*
*
*
*
*
Connected Load
202.0
*
*
Estimated Demand
162.0
*
*
*
*
Total;
*
*
Connected Load
227.0
*
*
Estimated Demand
182.0
*
*
*
*
Areas (SF):
*
*
Gross area including mechanical
*
*
equipment room
10,400
*
*
*
*
*
*
/))))))))))))))))))))))))))))))))))))))))0)))))))0))))))))))))))))))0))))))))1
* TITLE
* DATE * FACILITY PLATE * SHEET *
*
Air Passenger Terminal Facility * 11/92 *
* 3 OF 3 *
141-11
*
*
*
*
*
Design Notes
.))))))))))))))))))))))))))))))))))))))))2)))))))2))))))))))))))))))2))))))))-
163