2-5.2 New and Replacement Construction. The model STATEMENT OF WORK is the standard for
development of new and replacement UEPH Complexes and associated facilities. Local options for
editing are shown in brackets where applicable. USACE design activities should edit the STATEMENT
OF WORK to reflect site specific conditions. Upgrades of the stated criteria in response to installation
requests must have been itemized and the required funding identified on the programming documents.
2-5.2.1 Where an installation expresses a particular desire for a finish or material, that information can be
included in the Statement of Work and identified as a possible material quality increase (betterment) for
additional consideration during the Phase 2 evaluation. Following that identification, a statement must be
included that this identification is not authorization to exceed the maximum construction funds available
for this project as indicated in Section 00010 of the solicitation.
2-5.2.2 Force Protection and Anti-Terrorism Considerations. All new construction and major renovation
projects will require construction in accordance with applicable DoD standards.
||content||
\ Project design and
construction shall comply with UFC 4-010-01 Department of Defense Minimum Antiterrorism Standards
for Buildings and UFC 4-010-10 Department of Defense Minimum Antiterrorism Standoff Distances for
Buildings. [Design District shall investigate additional applicable requirements and insert into the
Statement of Work as needed.] /1/
2-5.2.3 Additions of prescriptive requirements to the statement of work is strongly discouraged as
prescriptive requirements decrease the flexibility and innovation possible with the design build
procurement methodology.
2-5.3 Using the STATEMENT OF WORK for Renovation.
2-5.3.1 Design Objectives and Criteria References. The intent of this document is to provide the Army
with facilities which closely approximate similar facilities in the other DoD Armed Forces and which are
comparable with those available in the commercial market in the United States. The technical criteria
contained in the STATEMENT OF WORK rely on industry standards as references whenever possible to
provide facilities comparable to private (commercial) construction. Objectives and criteria references are
the same for new, replacement, and renovated construction.
2-5.3.2 Site Planning. The objectives of site planning are the same for new, replacement, and renovated
construction. The goal is to provide each soldier with an appropriate, attractive environment in which to
live and function as a member of the Armed Forces.
The concept is to provide a "home" for the
unaccompanied soldier with respect to living space, recreation space, dining facilities, administrative
spaces, and supporting functions which are separate and distinct from the soldier's work area.
2-3