Project Name
Project Number
UEPH Complex
Statement of Work
26 November 2001
TABLE 4-1 Soil Compaction
Subgrade Preparation, Fills,
Compaction Requirements
(Percentage of Maximum Density)
Streets, Paved Areas, Bike
90
Paths
Sidewalks
85
Grassed Areas
80
The requirements shall be verified or modifications recommended by the consulting professional
geotechnical engineer in the report wherever engineering, soils, or climatic factors indicate the
necessity. Any modification to the stated compaction requirements shall require the approval of the
Contracting Officer.
4-1.3
Capillary Water Barrier. A capillary water barrier is required for all interior slabs on
grade, including garages, carports and storage rooms. As a minimum, the capillary water barrier
shall [Define minimum requirements.]
4-1.4
Soil Treatment. [If not required insert "...(DELETED)." and delete remainder of text.]
Soil treatment for termites shall be by the chemical method. Methods and extent of protection
required are as follows: [Insert project specific requirements.]
4-1.5
Decay Treatment. Decay treatment shall apply to the following: [Insert project specific
requirements.]
4-1.6
Radon Mitigation. The design and construction of
foundation walls, slabs, and crawl
spaces shall include provisions for the reduction of radon entry and facilitate its removal. Radon
mitigation shall comply with the requirements of ASTM E1465. [If not required, insert "...Deleted"."
and delete remainder of text. Design District technical specialists can contact Mr. David Price of
EPA's Indoor Environments Division, 202-564-9447 regarding suggested language concerning
indoor air quality and radon mitigation].
4-2
EROSION AND SEDIMENT CONTROL. Erosion and Sediment Control Facilities shall
be required in accordance with [Insert state or local agency having jurisdiction and reference any
applicable manual(s)], as specified in the manual entitled [insert criteria manual title].
4-3
DEMOLITION. Existing facilities scheduled for demolition includes [insert description or
reference attached sketches]. [The following demolished materials shall [become][remain] the
property of the [Contractor][Government: include installation list of recycled materials], unless
otherwise indicated or specified.] Materials not owned by the Government and not used in
construction shall be disposed of [off][on] government property. Obtain required demolition permits
[and disposal permits] from [Insert appropriate agency having jurisdiction and reference any
applicable manual(s)]. Obtain approval of the disposal site from the contracting officer[ and submit
haul tickets for material disposed of off of Government property].
4-4
CLEARING AND GRUBBING. Clear and grub all trees and vegetation necessary for
construction; but, save as many trees as possible. [All timber removed from the project site shall
[become][remain] the property of the [Contractor] [Government], unless otherwise indicated or
SOW-87