UFC 4-730-01
7 April 2006
including change 1, 20 June 2006
Exception: Also coordinate the interior (and exterior) design with the following Service-
specific standards or agencies:
Army. DG 1110-3-122, and Installation Design Guide Standards;
Navy and Marine Corps. UFC 3-100-10N,; and
Air Force. USAF Interior Design Guide, applicable Major Command and
Installation design standards.
In moist climates, do not cover the inside of exterior walls with impervious
materials such as mirrors or vinyl wall coverings. This will help prevent mold
development in the wall.
Table 3.1 provides a finish schedule for FSCs.
TABLE 3-1. FINISH SCHEDULE
General Space
Floor
Base
Walls
Ceiling
Notes
Lobby and Waiting
CPT/QT/CT
CT/QT/VB
Note 1
ACP/GWB
Note 2
Classroom
CPT/VCT
VB
GWB
ACP
Office/Clinical
CPT
VB
GWB
ACP
Lending Locker
SCF
None/VB
CMU/GWB
None/ACP
Kitchen
VCT
VB
CT/GWB
ACP/GWB
Note 3
Toilets
CT
CT
CT/GWB
GWB
Key:
GSU Glazed Structural Wall
SCF Sealed Concrete Floor
CMU Concrete Masonry Unit
GWB Gypsum Wall Board
SV Sheet Vinyl, slip resistant
CPT Carpet
GWC Glazed Wall Coating
VB Vinyl or Rubber Wall Base
CT Ceramic Tile
QT Quarry or Stone Tile
Notes:
Note 1 Walls in public areas may be made of a variety of durable materials such as brick or split block
Note 2 Child Play area should be CPT, VCT, and/or SV
Note 3 Moisture-resistant Ceiling Panel system
3-5
SERVICES. Also see paragraph 3-9 for information on sustainable design
and energy consumption.
3-5.1
Plumbing. Design domestic hot and cold water, sanitary and storm
drainage, propane, fuel oil, or natural gas systems to meet the requirements of local
Installation standards and UFC 3-420-01.
3-5.2
Heating, Ventilating, and Air Conditioning (HVAC). Design the HVAC
system to meet the requirements of the most current edition of the International
Mechanical Code (IMC); UFC 3-410-01FA, Design: Heating, Ventilating, and Air
3-3