high-risk activities (e.g., climbing wall). Provisions for an alarm system must be justified
during the planning/programming process.
2-8.4.2
Closed Circuit Television (CCTV). Consider providing a CCTV system.
Provisions for a CCTV system must be justified during the planning/programming
process.
Service requirements vary on CCTV systems. Note the following
criteria:
2-8.4.2.1
Navy. Conduit (minimum 19 mm (.75 in.)) and cabling shall be provided in
the Indoor Display Area with the central monitors located in the offices. The conduit
shall be used to accommodate government-furnished/government-installed, locally-
funded video equipment. This may require outlets higher in the ceilings, walls or both.
Electrical service shall be provided adjacent to anticipated location of cameras and
monitors.
2-8.4.2.2
Marine Corps. Provide the entire CCTV system including cameras,
monitors, conduit, cabling, power, and junction boxes for CCTV system.
2-9
SITE WORK.
2-9.1
Landscaping. Landscaping should reflect the programs offered and the
local geographical environment. The plant selection should be easy to maintain and
enhance the visual quality of the facility in all seasons. Native species are preferred.
Do not use poisonous plants.
2-9.2
Site Lighting. Ensure that parking areas and the compound have
adequate lighting for safety and security measures.
2-9.3
Outdoor Activities. If space permits, consider providing activities that
support the ORP. These activities should relate to the facility site plan and contribute to
the image and theme of the facility. However, consider that some of these activities
may be "attractive nuisances" and may need to be secured for safety reasons.
Examples are as follows:
Single track, dirt mountain bike and running trails constructed of and on
mineral soil
Environmental interpretive trails
Challenge courses
Climbing walls/towers and bouldering walls
Snowboard/ski terrain parks
Wave pools/whitewater parks
BMX park/tracks
2-15