providing	any	updates	of	these	documents	as	the	project	progresses.
1-5.1.4  Approving	concept	and	later	designs	to	certify	compliance	with	functional	
requirements.
1-5.1.5  Developing	additional	information,	as	required,	such	as	telephone	needs,	
special	electrical	requirements	and	equipment	specifications.
1-5.2
The	Design	Agency	is	responsible	for	the	following:
1-5.2.1  Preparing	a	design	that	provides	for	a	complete	and	usable	facility,	including	
all	equipment,	fixtures	and	furnishings	except	those	specifically	designated	as	
Government-furnished.
1-5.2.2  Incorporating	the	functional	requirements	of	the	Using	Service	and	USAR	
Installation	into	the	project	design.
1-5.2.3  Developing	a	design	responsive	to	the	criteria	in	this	Guide	and	the	project	
documentation,	and	preparing	all	submittals	required	by	the	USAR	Design	Process	and	
Submittal	Requirements,	and	the	project	Scope	of	Work.
1-5.2.4  Justifying,	in	the	project	Design	Analysis,	any	issues	of	design	which	do	not	
follow	this	Guide	and	other	project	documentation.
1-5.2.5  Incorporating	the	quality	standards	for	the	overall	design	as	described	in	this	
Guide	and	other	criteria	for	the	project.
1-5.2.6
Identifying	the	applicable	codes	and	regulations,	and	
Figure 1-4
Figure
ensuring	that	the	design	is	in	compliance	with	them.
ARRTC VOQ,
Ft. McCoy,
1-5.2.7
Preparing	cost	estimates,	and	ensuring	that	the	
Wisconsin
design	will	provide	a	fully	functional	facility	within	the	project	
construction	cost	limit	(CCL).	Optional	bid	items	may	be	required	
to	ensure	that	a	base	bid	within	the	construction	cost	limit	can	be	
achieved.	Any	such	options	must	be	planned	such	that	the	facility	
is	complete	and	usable	without	their	inclusion.
1-5.2.8
Preparing	a	draft	of	DD	Form	1354,	Transfer	and	
Acceptance	of	Military	Real	Property.
1-5.2.9
Preparing	any	surveys	and/or	geotechnical,	
environmental,	sustainable	design	or	other	investigations	
identified	in	the	project	Scope	of	Work.
1-5.2.10 Developing	design	analyses,	calculations,	and	other	information	that	supports	
and	explains	the		project	design.
1-5.2.11 Identifying	issues	that	will	deserve	special	attention	during	project	
4