(b) The period of this warranty shall commence upon final completion and the Government's acceptance
of the work, or in the case of the Government's beneficial occupancy of all or part of the work for its
convenience, prior to final completion and acceptance, at the time of such occupancy.
(c) This design warranty shall be effective from the above event through the Statue of Limitations and
Statute of Repose, as applicable to the state that the project is located in.
(d) The rights and remedies of the Government provided for under this clause are in addition to any other
rights and remedies provided in this contract or by law.
(End of Clause)
SEQUENCE OF DESIGN/BUILD CONSTRUCTION
This SCR may also be referred to as "Sequence of Work". Two different Special Contract Requirements
were developed to address this issue. Use the first SCR when all design or most of the design must be
completed prior to allowing construction to begin. Use the second SCR when allowing "fast-track" design-
build. Fast track is a term used to describe design and construction sequencing when the D-B
incrementally completes and submits portions of the design, in "design packages", for Government
review. Once the Government completes its review and all review comments are resolved, the ACO/COR
will clear that design package for construction . Thus, in fast track design-build, design and construction
can proceed concurrently.
The D-B RFP will include only one of the two SCR's.
This information can also be alternately be
addressed in Section 01012- "DESIGN AFTER AWARD".
SCR___
SEQUENCE OF DESIGN-CONSTRUCTION AUG 1997
(a)
After receipt of the Contract Notice to Proceed (NTP) the Contractor shall initiate design, comply
with all design submission requirements as covered under Division 01 General Requirements, and obtain
Government review of each submission. No construction may be started, <with the exception
of....clearing, etc...> until the Government reviews the Final Design submission and determines it
satisfactory for purposes of beginning construction. The ACO or COR will notify the Contractor when the
design is cleared for construction. The Government will not grant any time extension for any design
resubmittal required when, in the opinion of the ACO or COR, the initial submission failed to meet the
minimum quality requirements as set forth in the Contract.
(b)
If the Government allows the Contractor to proceed with limited construction based on pending
minor revisions to the reviewed Final Design submission, no payment will be made for any in-place
construction related to the pending revisions until they are completed, resubmitted and are satisfactory to
the Government.
(c) No payment will be made for any in-place construction until all required submitttals have been made,
reviewed and are satisfactory to the Government.
(End of Clause)