Use the following Special Contract Requirement for fast track design-build contracts, in lieu of the above
clause. This material can alternately be included in Section 01012-Design After Award.
SCR___
SEQUENCE OF DESIGN-CONSTRUCTION (FAST TRACK)
(a)
After receipt of the Contract Notice to Proceed (NTP) the Contractor shall initiate design, comply
with all design submission requirements as covered under Division 01 General Requirements, and obtain
Government review of each submission. The contractor may begin construction on portions of the work
for which the Government has reviewed the final design submission and has determined satisfactory for
purposes of beginning construction. The ACO or COR will notify the Contractor when the design is
cleared for construction. The Government will not grant any time extension for any design resubmittal
required when, in the opinion of the ACO or COR, the initial submission failed to meet the minimum
quality requirements as set forth in the Contract.
(b)
If the Government allows the Contractor to proceed with limited construction based on pending
minor revisions to the reviewed Final Design submission, no payment will be made for any in-place
construction related to the pending revisions until they are completed, resubmitted and are satisfactory to
the Government.
(c) No payment will be made for any in-place construction until all required submitttals have been made,
reviewed and are satisfactory to the Government.
(End of Clause)
CONSTRUCTOR'S ROLE DURING DESIGN
This SCR outlines the role of the Contractor's key construction management staff during the design
process.
SCR___
CONSTRUCTOR'S ROLE DURING DESIGN JUN 1998
The Contractor's construction management key personnel shall be actively involved during the
design process to effectively integrate the design and construction requirements of this contract.
In addition to the typical required construction activities, the constructor's involvement includes, but
is not limited to actions such as: integrating the design schedule into the Master Schedule to
maximize the effectiveness of fast-tracking design and construction (within the limits allowed in the
contract), ensuring constructability and economy of the design, integrating the shop drawing and
installation drawing process into the design, executing the material and equipment acquisition
programs to meet critical schedules, effectively interfacing the construction QC program with the
design QC program, and maintaining and providing the design team with accurate, up-to-date
redline and as-built documentation. The Contractor shall require and manage the active
involvement of key trade subcontractors in the above activities.
(End of Clause)
This is an optional SCR to emphasize the D-B's liability for the adequacy of the design in the D-B
contract.