Project Name
Project No. ___________
UFC 4-721-11.1, UEPH Complexes, 26 Nov 01
SCR___
SEQUENCE OF DESIGN-CONSTRUCTION AUG 1997
(a)
After receipt of the Contract Notice to Proceed (NTP) the Contractor shall initiate design, comply
with all design submission requirements as covered under Division 01 General Requirements, and obtain
Government review of each submission. No construction may be started, <with the exception
of....clearing, etc...> until the Government reviews the Final Design submission and determines it
satisfactory for purposes of beginning construction. The ACO or COR will notify the Contractor when the
design is cleared for construction. The Government will not grant any time extension for any design
resubmittal required when, in the opinion of the ACO or COR, the initial submission failed to meet the
minimum quality requirements as set forth in the Contract.
(b)
If the Government allows the Contractor to proceed with limited construction based on pending
minor revisions to the reviewed Final Design submission, no payment will be made for any in-place
construction related to the pending revisions until they are completed, resubmitted and are satisfactory to
the Government.
(c) No payment will be made for any in-place construction until all required submitttals have been made,
reviewed and are satisfactory to the Government.
(End of Clause)
Use the following Special Contract Requirement for fast track design-build contracts, in lieu of the above
clause. This material can alternately be included in Section 01012-Design After Award.
SCR___
SEQUENCE OF DESIGN-CONSTRUCTION (FAST TRACK)
(a)
After receipt of the Contract Notice to Proceed (NTP) the Contractor shall initiate design, comply
with all design submission requirements as covered under Division 01 General Requirements, and obtain
Government review of each submission. The contractor may begin construction on portions of the work
for which the Government has reviewed the final design submission and has determined satisfactory for
purposes of beginning construction. The ACO or COR will notify the Contractor when the design is
cleared for construction. The Government will not grant any time extension for any design resubmittal
required when, in the opinion of the ACO or COR, the initial submission failed to meet the minimum
quality requirements as set forth in the Contract.
(b)
If the Government allows the Contractor to proceed with limited construction based on pending
minor revisions to the reviewed Final Design submission, no payment will be made for any in-place
construction related to the pending revisions until they are completed, resubmitted and are satisfactory to
the Government.
(c) No payment will be made for any in-place construction until all required submitttals have been made,
reviewed and are satisfactory to the Government.
(End of Clause)
CONSTRUCTOR'S ROLE DURING DESIGN
This SCR outlines the role of the Contractor's key construction management staff during the design
process.