CONSTRUCTOR'S ROLE DURING DESIGN JUN 1998
The Contractor's construction management key personnel shall be actively involved during the
design process to effectively integrate the design and construction requirements of this contract.
In addition to the typical required construction activities, the constructor's involvement includes, but
is not limited to actions such as: integrating the design schedule into the Master Schedule to
maximize the effectiveness of fast-tracking design and construction (within the limits allowed in the
contract), ensuring constructability and economy of the design, integrating the shop drawing and
installation drawing process into the design, executing the material and equipment acquisition
programs to meet critical schedules, effectively interfacing the construction QC program with the
design QC program, and maintaining and providing the design team with accurate, up-to-date
redline and as-built documentation. The Contractor shall require and manage the active
involvement of key trade subcontractors in the above activities.
(End of Clause)
This is an optional SCR to emphasize the D-B's liability for the adequacy of the design in the D-B
contract.
SCR___
RECOMMENDED INSURANCE COVERAGE
The Design-Build Contractor's attention is invited to the contract requirements concerning
"RESPONSIBILITY OF THE CONTRACTOR FOR DESIGN" and "WARRANTY OF CONSTRUCTION
WORK". These requirements vest in the Contractor complete responsibility for the professional quality,
technical accuracy, and coordination of all design, drawings, specifications and other work or materials
furnish by his in-house or consultant forces. The Design-Build Contractor must correct and revise any
errors or deficiencies in his work, notwithstanding any review, approval, acceptance or payment by the
Government. The Contractor must correct and change any work resulting from his defective design at no
additional cost to the Government. The requirements further stipulate that the Design-Build Contractor
shall be liable to the Government for the damages to the Government caused by negligent performance.
Though not a mandatory requirement, this is to recommend that the Design-Build Contractor investigate
and obtain appropriate insurance coverage for such liability protection.
(End of Clause)
TRAINING
This is suggested wording for a training requirement. This requirement can alternately be included
elsewhere in the contract, for example, in Section 01012, "DESIGN AFTER AWARD". It is highly
recommended that training be video taped for use by future maintenance personnel.
SCR___
TRAINING FEB 2000
The Contractor shall provide operational and maintenance training for all systems furnished under this
contract for the operating and maintenance personnel. The system manufacturer shall conduct the
training, where feasible. All operation and maintenance manuals shall be submitted and approved prior
0800 - 9