UM = EA
Construction Cost Factor (CCF)
8,670.00/EA, based on data provided by USACE. The SF CCF for FAC 3711 was multiplied
by the reference size of 2,000 SF to obtain an EA value. Values were deflated to FY04 $ using a deflation
factor of 0.985.
Sustainment Cost Factor (SCF)
,221.68/EA, the sustainment factor was calculated using the SCF from FAC 3711 (.26) times
the reported average size of 1,868 SF, as no other auditable data was available.
No Layout Available