Project Name
Project No. ___________
UFC 4-214-02, TEMF, 24 July 03
m. Building Structural Systems. This subfactor evaluates the structural systems and sub-systems
proposed for installation in the facilities. While no detail drawings or calculations are required or desired,
this subfactor will evaluate the narrative descriptions of the structural systems proposed. This is GO-NO
GO subfactor.
FACTOR 2-3: SITE DESIGN CONSIDERATIONS.
This factor considers the layout and planning of the site and various specialties which comprise a good
site development plan. The goal and direction of the TEMF program is to provide for an efficient, well
organized facility and supporting paved area configuration which provide the necessary space and
arrangement to allow military and civilian personnel to effectively service tactical equipment.
All
elements of site design will be considered in this factor, with the exception of the design and materials
utilized for utility systems which will be evaluated under a different factor. The following subfactors shall
be considered in evaluation this factor. The levels of importance are as follows:
Subfactor a is considered the most important subfactor.
Subfactor b is slightly less important than subfactor a.
Subfactor c is slightly less important than subfactor b.
Subfactor d is slightly less important than subfactor c.
Subfactor e is slightly less important than subfactor d.
a. Area Development Plan. This subfactor evaluates the overall development concept proposed in the
Offeror's plan with respect to the placement and orientation of the facilities, parking areas, hardstands,
efficient arrangement of facility access points for vehicles and vehicle circulation spaces, site lighting, and
other aspects which comprise the overall site development. Area development plan should incorporate
the module designs provided in the solicitation. Proposals which reflect the design intent and direction
as outlined in the Statement of Work will receive the most consideration during the evaluation process.
b. Force Protection Considerations. This subfactor evaluates the inclusion of the site restraints
imposed by the Force Protection requirements in the Statement of Work into the Offeror's proposal.
The proposal must address this subfactor specifically.
If a proposal is rated "unacceptable" in this
subfactor the proposal may be eliminated from further consideration.
c. Grading. This subfactor evaluates the proposed grading alterations to the existing site to suit the
new development.
The Offeror's proposal will be evaluated on the amount and type of site regarding
required as well as the provision for positive storm drainage away from the new facilities and parking
areas.
d. Paved Areas. This subfactor evaluates the provision of parking for the new facilities.
In this
subfactor the following items should be considered:
(1)
Proximity to new facilities
(2)
Layout of Parking Areas
(a)
Internal Circulation considerations
(b)
Clear exit and entrance pathways
(c)
Facility access points and vehicle circulation paths
(d)
Separation of parking areas entrances/exits from street intersections.
e. Landscaping. This subfactor evaluates the design, quality, quantity, and location of all planting
materials in the proposal.
Considerations should include the use of landscaping as screening for
exterior equipment and for the facility operations as a whole. The following items shall be considered in
(1) Does the proposal include landscaping materials to provide screening for the facility from adjacent
structures and uses?
00120 - 10