FACTOR 2-6: OFFEROR MANAGEMENT PLANS AND SCHEDULES.
This factor evaluates the Offeror's Project Management Plans as well as the proposed schedule for
completion of the entire design-build project. Through this factor the Government will evaluate the
Offeror's understanding of the solicitation provisions with respect to an integrated design-build process
and the associated quality control, scheduling, coordination, and contract close out provisions. Each of
the subfactors below is approximately equal in importance in the evaluation.
a. Quality Control Plan. The sample quality control plan provided by the Offeror will be reviewed and
evaluated for inclusion of specific quality control practices and requirements necessary for the successful
completion of all phases of this project. These phases include design stages as well as construction
specialties. Offeror's plan must show the inclusion of the Corps Three Phase Inspection process and
address the implications and operations of the Quality Control Plan and it's integration with the Quality
Assurance Operations performed by the Government. The personnel and qualifications of the individuals
performing in the Quality Control organization will be evaluated under the Phase 1 submission, however,
if personnel changes have occurred since the Phase 1 submittal, these individuals must be evaluated as
part of the Phase 2 evaluation process.
b. Schedule Information. The schedule will be evaluated to assess the inclusion of "fast tracking" and
the rational of how the Offeror intends to comply with the submitted schedule. The schedule must reflect
a single task oriented structure for both design and construction. The schedule will be reviewed for
completeness and the inclusion of required milestones. A schedule which improves on the Government
supplied maximum duration will be considered more favorably during the evaluation.
c. Closeout Plan. The Offeror's closeout plan will be reviewed and evaluated to determine the Offeror's
understanding the close out requirements of the solicitation. Particular emphasis will be placed on O&M
Manual production and Installation Staff training methods and processes.
d. Sub-Contracting Plan. The Government will evaluate the Offeror's proposed subcontracting plan
will be evaluated in terms of achieving the required special emphasis group participations and the
completeness and rational for the plan proposed. Offerors who are not required to submit a
subcontracting plan (ie Small Business concerns) will be assigned a rating equal to the highest evaluation
of any subcontracting plan submitted in response to this solicitation.