UFC 4-214-02, 24 Jul 03
stand of turf shall be repaired as soon as turfing conditions permit.
3-12.2.7
Satisfactory Stand of Turf.
3-12.2.7.1 Seeded Lawn Area. A satisfactory stand of turf from the seeding operation for a lawn
area is defined as a minimum of 160 grass plants per square meter. Bare spots shall be no larger
than 150 mm square. The total bare spots shall not exceed two (2) percent of the total seeded area.
3-12.2.7.2 Seeded Field Area. A satisfactory stand of turf from the seeding operation for a field
area is defined as a minimum of 100 grass plants per square meter. The total bare spots shall not
exceed two (2) percent of the total seeded area.
3-12.2.7.3 Sodded Area. A satisfactory stand of turf from the sodding operation is defined as living
sod uniform in color and texture. Bare spots shall be no larger than
50 mm [2 in] square.
3-12.2.7.4 Sprigged Area. A satisfactory stand of turf from the sprigging operation is defined as a
minimum of 20 sprigs per square meter. Bare spots shall be no larger than 225 mm square. The
total bare spots shall not exceed two (2) percent of the total sprigged area.
3-12.2.8 Maintenance During Establishment Period. The maintenance of the turfed areas
shall include eradicating weeds, eradicating insects and diseases, protecting embankments and
ditches from erosion, maintaining erosion control materials and mulch, protecting turf areas from
traffic, mowing, watering, post-fertilization, and replacing unsatisfactory turf areas.
3-13
SPRINKLER AND/OR IRRIGATION SYSTEM. [Insert installation standards for
sprinkler and irrigation systems.] [Provide a complete permanent automatic irrigation system with
controllers covering all common planting areas and slopes. Design the system to function with
available water pressure. Investigate and employ methods of irrigation based on sustainable
design principles, where practical and feasible.] [In areas where sprinkler and/or irrigation systems
are not required, delete the paragraph text and insert, "Not required"].
[3-14
VEHICLE/EQUIPMENT WASHDOWN AREA. [Each installation shall determine the
feasibility of including washdown areas as part of the TEMF project.] Provide a [concrete]
paved vehicle/equipment washdown area at a location on the site. Provide [3] washing
station[s] with a double hose bib and outdoor rated electrical outlet at each station for activity
furnished/owned portable pressure washers. Each washing station shall be a minimum of 6 m x
12 m [insert alternative site specific size requirement] in size. Each washdown area shall be
graded to drain all surface water to an open channel or trench drain. Open channel or trench
drain shall be of suitable design to support easy cleaning and maintenance. All drainage water
shall be directed first to a grit removal device and then to an oil water separator. All drainage
water shall discharge to the[ sanitary sewer] [storm sewer ]system. [A post indicator valve shall
be installed to bypass the sanitary sewer system and allow normal stormwater to flow to the
storm sewer system.] [Additionally, provide [compressed air] [insert other required features
specific to the site] at each washing station.]]
[3-15
IBCT/Transformation criteria. If required, include in this paragraph, underground PVC conduit
with pull wire, handholes, termination boxes, and vehicle-rated covers necessary to
accommodate government provided communications cables to hardstand vehicle parking
locations.]
SOW-45