UFC 4-721-11.1
26 Nov 01
6-6 AUTHORITY TO ADVERTISE ACTIVITIES MATRIX.
6-6.1 The PM will ensure that the following activities are accomplished:
Activity Lead
AUTHORITY TO ADVERTISE ACTIVITIES
Customer
P PA
CS
M /PE
a. Verify that the date, time, and location for proposal receipt is
included in the RFP.
X
X
b. Verify that all RFP review comments have been incorporated or
otherwise resolved to the reviewer's satisfaction.
X
X
c. Review basis of award stated in the RFP to ensure it is clear.
X
X
X
d. Review the explanation of the evaluation process in the RFP to
ensure that it is clearly defined.
X
X
X
e. Verify that the RFP had a final Contracting and Legal review
X
X
f. Prepare Source Selection Guidelines for review and approval.
X
X
g. Verify that Source Selection Plan is completed.
X
X
REFERENCES
6-1 FAR Part 15, "Contracting By Negotiation"
6-2 FAR Part 36.3 "Two-Phase Design-Build Selection Procedures"