individuals with experience in design build construction. The evaluation team shall consist of at least
four, and not more than six individuals with appropriate experience in design and construction projects.
7-1.5.1 Composition of the Evaluation Team. The evaluation team shall be composed of not less than
four and not more than six members representing the USACE design activity, the USACE construction
activity, the Installation DPW, the ACSIM, and one or more technical experts from another District with
design build experience. As soon as the names of the evaluation team members are finalized, the PA/PE
will have their names added to the list of RFP package holders, and will provide a copy of the RFP and
amendments to them
||content||
\ prior to /1/ the evaluation.
7-1.5.2 Travel, per diem, and salary costs for evaluation team member's participation are funded from
project design costs. Military Interdepartmental Purchase Requests (MIPR) should be forwarded to the
participating evaluation team members in sufficient time to permit processing of travel orders.
7-2 LEGAL AND CONTRACTING REVIEW.
7-2.1 General Conformity.
||content||
\ Proposals must be opened by the Contracting Division. /1/ Proposals
must not be opened publicly. The Contracting Division will also review proposals to ensure that the
required personnel and performance data for each proposal are provided in accordance with Section
00110, PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS.
7-2.2 Cost Information. No cost information shall be included with the Phase 1 proposal.
7-2.3 Non-Disclosure. All evaluators are required to sign a certificate which includes procurement
integrity, nondisclosure, standards of conduct, and conflict of interest provisions before they receive
proposals for review. In addition to reviewers,
||content||
\ any and /1/ all personnel who see the proposals must
sign the required certificates.
7-3 EVALUATING OFFEROR PERFORMANCE CAPABILITY.
7-3.1 An offeror's performance capability may be determined by evaluating design, construction and
management personnel qualifications, relevant corporate experience, past performance information,
financial capability, and organizational structure proposed for the project. FAR 15.304 (reference 8-3)
specifically permits evaluating such relevant factors.
The management review should involve
Government representatives experienced in construction management and design.
Complete
documentation of strengths and weaknesses of each proposal for each factor and subfactor is extremely
important. A performance capability evaluation format is provided at Appendix A.
It is extremely
important to set up and follow a prescribed evaluation process to avoid possible potential conflicts later
and avoid time consuming protests.
7-3.2 Past Performance. As a part of the Phase 1 evaluation process the Government representatives
shall review the offeror reference questionnaires which have been provided to the Contract Specialist.
Each proposal must have at least three reference questionnaires received. Where less than three are
received, the offeror will receive a lesser rating for this factor. It is the offeror's responsibility to ensure
that his or her references return the required information.
If a particular offeror does not have past
performance information to provide, this offeror should so indicate in his/her proposal and shall be
provided a neutral rating. The lack of past performance information is not the same as the failure of an
identified reference to complete and provide the reference questionnaire required.
7-3.3 Recent Relevant Experience. The offeror shall provide a list of past projects on which they
involved within the last three years which the offeror feels are relevant to the project under consideration.
Design Districts may lengthen the amount of time permissible for inclusion of recent relevant experience
projects.
7-3.4 Key Personnel. This information provided at Phase 1 will only address the key individuals for
construction and design.
For Construction, these individuals typically include the prospective