12-3
SPRINKLER SYSTEM.
12-3.1
Wet pipe sprinkler system. [ The entire building ] [ describe spaces to be sprinkled ]
shall be protected by a wet pipe sprinkler system. Sprinkler system shall be designed and
installed in accordance with the provisions of NFPA 13, Standard for the Installation of Sprinkler
Systems. UEPH building four stories or less may be protected by a wet pipe sprinkler system
designed and installed in accordance with the provisions of NFPA 13R, except that buildings,
which use the sprinkler system to increase allowable floor area based on particular construction
type, shall be designed and installed in accordance with the provisions of NFPA 13. Provide
hydraulic calculations to support design of the system.
12-3.2
Dry pipe sprinkler system. Provide dry pipe sprinkler system for [ describe spaces to
be sprinkled ]. Sprinkler system shall be designed and installed in accordance with the
provisions of NFPA 13, Standard for the Installation of Sprinkler Systems. Provide hydraulic
calculations to support design of the system.
12-3.1
Sprinkler Heads. All sprinkler heads located in finished areas shall be recessed
pendent type.
12-4
FIRE PUMP.
12-4.1
Electric fire pump. Provide electric driven fire pump and controllers in accordance
with NFPA 20.
12-4.2
Diesel fire pump. Provide electric driven fire pump and controllers in accordance
with NFPA 20. Provide a diesel fuel tank in accordance with NFPA criteria.
12-5
STANDPIPE AND HOSE SYSTEM. Provide standpipe and hose system for all
buildings in accordance with NFPA criteria.
12-6
BUILDING CONSTRUCTION. Comply with requirements of International Building
Code and NFPA 101Life Safety Code.
12-6.1
Fire Extinguishers and Cabinets. Provide portable fire extinguishers in
accordance with NFPA 10. Provide semi-recessed aluminum fire extinguisher cabinets with
clear view panel in public areas, and where indicated in functional and area requirements.
Provide fire-rated cabinets in fire-rated wall assemblies.
12-6.2
Interior Wall and Ceiling Finishes.
Wall and ceiling finishes and movable
partitions shall conform to the requirements of the IBC and NFPA 101, except as follows [The
following, more stringent, interior finish requirements are included to comply with MilHdbk
1008C, Fire Protection for Facilities Engineering, Design, and Construction]:
12-6.2.1
Interior finish for exits, exit passageways, sleeping rooms shall be Class A only.
12-6.2.2 Flame spread (FS) and smoke development (SD) shall be tested in accordance with
ASTM E84. Tests shall not exceed FS rating of 25 and SD rating of 50 for Class A materials;
FS rating of 75 and SD rating of 100 for Class B materials; and FS rating of 200 and SD rating
of 200 for Class C materials. Class C materials shall only be permitted in fully sprinklered
buildings.
SOW-151