UFC 3-460-03
21 JANUARY 2003
2. Check tape cable for wear or fraying caused by
ٱ
rubbing on the cover.
Sample Hatch (Internal Floating Roof)
ٱ
1. Check overall condition.
2. If equipped with a fabric seal, check for automatic
ٱ
sealing after sampling.
3. If equipped with a recoil reel opening device, check for
ٱ
proper operation.
Roof-Mounted Vents (Internal Floating Roof)
ٱ
Check condition of screens, locking pins, and pivot pins.
Gauging Platform Drip Ring
On fixed-roof tanks with drip rings under the gauging
ٱ
platform or sampling area, inspect drain return to the tank
for plugs.
Emergency Roof Drains
Inspect vapor plugs for emergency drain; ensure that seal
ٱ
fabric discs are slightly smaller than the interior diameter
of the pipe, and that fabric seal is above the liquid level.
Removable Roof Leg Racks
ٱ
Check for racks on roof.
Vacuum Breakers
Record size, number, and type of vacuum breakers.
ٱ
Inspect vacuum breakers; if high legs are set, check for
setting of mechanical breaker in high-leg position.
Rim Vents
ٱ
1. Check condition of the screen on the rim vent cover.
2. Check for plating off or removal of rim vents where
ٱ
jurisdictional rules do not permit removal.
Pontoon Inspection Hatches
1. Open pontoon inspection hatch covers and check
ٱ
inside for pontoon leakage.
2. Test for explosive gas (an indicator of vapor space
ٱ
leaks).
Checklist derived from API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction
153