UFC 3-600-02
1 January 2001
Table 2-19. Carbon Dioxide Systems ITM Tasks (Continued)
Component
Tasks
Annual
6. Auxiliary Equipment
(Continued)
closers, dampers) operate properly
and are activated by the control panel.
2 Years
1. High Pressure Cylinders
1. Verify CO2 quantity by weighing
cylinders.
As Part of
Entire System
1. Visually Check:
Building
a. Check pipe hangers.
Inspection
b. Check heads for obstruction.
c. Check piping for leaks.
d. Check riser condition.
2. Ensure:
b. Panels secured and indicator
lamps functional.
c. Notification appliances in place.
d. Manual stations in place and
unobstructed.
e. Nozzles' covers in place.
2-26