UM = SF
Construction Cost Factor (CCF)
9.00/SF, based on data from TriService #10/6, and deflated to FY04 $ using deflation factor of
0.97.
Sustainment Cost Factor (SCF)
.60/SF, using the Whitestone MARS and a component list derived from a typical inventory size
of 30,000 SF. Pending receipt of MARS details from AMEDD, details will be published.