UM = SF
Construction Cost Factor (CCF)
1.42/SF, based on data provided from AFCESA and USACE, and a weighted average of the
Service's reported inventory of the various category codes in this FAC. Values were adjusted to FY04$
using the appropriate inflation/deflation factor.
Sustainment Cost Factor (SCF)
||content||
.23/SF, using the Whitestone MARS and a component list derived from the DoD typical
inventory size of 929 SF. Values are in FY04 $.
Replacement
Cost:
3,509
Building GSFT: 929
M&R Average Annual Cost Forecasts
Current Year
5 Year
20 Year
50 Year
PM & Minor Repair:
2
5
4
8
Unscheduled
3
7
4
1
Renewal &
Replacement:
0
2
8
Total M&R Costs:
5
3
0
||content||
,138
As % of replacement:
0.41%
0.51%
0.94%
1.10%
Per gsft:
||content||
.06
||content||
.23
Component
Quantity
UM
Wood Shingles, Unfinished- 1st Floor
1458
Sq Ft
Aluminum Fixed Window, 12 sf, 1st Floor
4
Each
Steel, Painted, Exterior Door
1
Each
Asphalt Shingle Roof
929
Sq Ft
Wood, Solid Core, Painted, Interior Door
1
Each
Sheetrock, Unstippled, Interior Wall Finish
50
Sq Ft
Concrete, Unfinished Flooring
929
Sq Ft
Sheetrock, Unstippled, Ceiling
929
Sq Ft
Flush Tank Water Closet
1
Each
Pipe & Fittings, 3/4" Copper, Cold Water
0.025
K Ln Ft
Pipe & Fittings, 6" Cast Iron
0.025
K Ln Ft
Fluorescent Lighting Fixture, 160w
10
Each
Receptacle, 120V, 15 Amp
8
Each
Wiring Device, Switch
3
Each
Smoke Detector
1
Each
Annual Sustainment Costs
.00
.00
.00
.00
.00
.00
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49
50 Year Life Cycle