Project Name
Project No. ___________
UFC 4-721-11.1, UEPH Complexes, 26 Nov 01
Contractor shall identify whether the submittal is for "Government Approval" or for "Government
Information" under the column "Remarks." The "final" Eng Form 4288, Submittal Register, shall be in
accordance with clause CONTRACTOR SUBMITTALS AND SUBMITTAL CONTROL in this section.
12.4 Reproduction: Upon Government approval of 100% design documents, the original will be
returned to the Contractor for reproduction purposes. The Contractor will be responsible for his own
reproduction as well as reproduction for Government use. The Government will require twice the
number of copies of the plans and specifications as were required for the review stages, no color
boards will be required. The originals will be retained by the Contractor for recording of as-built
conditions. Upon completion of the project, the original design documents corrected to reflect as-built
conditions will be supplied to the Government.
S
ection 01012 - Page 18