UFC 4-721-11.1, UEPH Complexes, 26 Nov 01
11.2.8.3 Specify all components of the Fire Suppression (FS) System in the FS section of the
specifications. Provide a clear description of how the system will operate and interact with other
systems such as the fire alarm system. Include a riser diagram on the drawings showing principal
components and interconnections with other systems. Include FS system components on drawing
legend. All components shown of floor plans shall be designated as FS system components (as
opposed to Fire Alarm components). Show the location of FS control panels, HVAC control devices,
sensors, and 120V power panel connections on the floor plans. Indicate zoning of areas by numbers
(1, 2, 3) and detectors subzoned for cross zoning by letter designations (A and B). Differentiate
between ceiling mounted and underfloor detectors with distinct symbols and indicate subzone of each.
11.2.8.4 Show location of telephone outlets (including pay phones) on the plans. Include legend and
symbol definition to indicate height above finished floor. Show Telephone Conduit System Riser
Diagram. Size conduit on Riser Diagram. Do not show conduit runs between backboard and outlets
on the floor plans. Underground telephone distribution conduit shall be shown on either the electrical
or electronic site plan.
11.2.8.5 Grounding System. The specifications and drawings shall completely reflect all of the design
requirements. The specifications shall require field tests (in the construction phase), witnessed by the
Contracting Officer, to determine the effectiveness of the grounding system. The design shall include
drawings showing existing construction. Verification of the validity of any existing drawings and/or any
other data furnished by the Government shall be the responsibility of the engineering services firm.
11.2.8.6 Provide a statement describing the extent of any exterior work such as telephone lines, cable
television (TV) distribution cables, duct banks, etc., outside of 5 feet from the building line.
11.2.8.7 Provide the name of the licensed corrosion engineer or NACE specialist. Provide the
following for cathodic protection systems:
Clearly define areas of structures or components in soil or water to be protected.
Type system recommended, comparison of systems, cost estimates showing all equipment
alternatives.
Calculations on all systems that are considered showing all information and descriptions.
11.2.8.7.1 Design of Cathodic Protection. The design shall clearly provide a thorough and
comprehensive specification and drawing. The design plans and specifications shall show extent of
the facilities to be protected, location and type of anodes, location of test points, details for
sectionalizing an underground piping system. This design shall be complete enough to purchase
equipment and build without design changes to meet criteria of protection.
11.2.8.8 Exterior work to be shown on electrical site plan.
Existing and new communications service lines, both overhead and underground, shall be
properly identified.
Show removals and relocations, if any.
11.2.8.9 Provide a descriptive narrative of all electronic systems that are required for project. Define
any hazardous areas (as defined in the National Electric Code) and indicate the type of equipment
proposed for use in such areas. Show the location of all electronic system panels, etc., on the floor
plans. Show the proposed riser diagrams for all systems. Sizes of all conduit, wires, cables, panels,
etc. Provide a complete symbol legend for all devices or equipment shown on the plans. For work
requiring removals or demolition, the designer shall show by use of drawings or narrative, how
demolition work is to be done.
S
ection 01012 - Page 13