Project Name
Project No. ___________
UFC 4-721-11.1, UEPH Complexes, 26 Nov 01
11.2.4.1 State the live loads to be used for design. Include roof and floor loads; wind loads, lateral
earth pressure loads, seismic loads, etc., as applicable.
11.2.4.2 Describe the method of providing lateral stability for the structural system to meet seismic
and wind load requirements. Include sufficient calculations to verify the adequacy of the method.
11.2.4.3 Furnish calculations for all principal roof, floor, and foundation members.
11.2.4.4 This submittal shall include drawings showing roof and floor framing plans as applicable.
Principal members will be shown on the plans. A foundation plan shall also be furnished showing
main footings and grade beams where applicable. Where beam, column, and footing schedules are
used, show schedules and fill in sufficient items to indicate method to be used. Show typical bar
bending diagram if applicable. Typical sections shall be furnished for roof, floor, and foundation
conditions. Structural drawings for proposals and submittals shall be separate from architectural
drawings.
11.2.4.5 Provide any computer analyses used shall be widely accepted, commercially available
programs and complete documentation of the input and output of the program.
11.2.4.6 Provide complete seismic analyses for all building structural components. Seismic
calculations shall clearly demonstrate compliance with all requirements set forth in the Statement of
Work.
11.2.5 Plumbing Systems
11.2.5.1 List all references used in the design including Government design documents and industry
standards.
11.2.5.2 Provide justification and brief description of the types of plumbing fixtures, piping materials
and equipment proposed for use.
11.2.5.3 Prepare detail calculations for systems such as sizing of domestic hot water heater and
piping; natural gas piping; [lp gas piping and tanks] [fuel oil piping and tanks].
11.2.5.4. Indicate locations and general arrangement of plumbing fixtures and major equipment.
11.2.5.5 Include plan and isometric riser diagrams of all areas including hot water, cold water, waste
and vent piping. Piping layouts and risers should also include natural gas (and meter as required), [LP
gas], [fuel oil] and other specialty systems as applicable.
11.2.5.6 Include equipment and fixture connection schedules with descriptions, capacities, locations,
connection sizes and other information as required.
11.2.6 Fire Protection/Suppression
11.2.6.1 List all references used in the design including Government design documents and industry
standards used to generate the fire protection analysis.
11.2.6.2 Classify each building in accordance with fire zone, building floor areas and height and
number of stories. This information shall be contained in the fire protection analysis.
11.2.6.3 Discuss and provide description of required fire protection requirements including
extinguishing equipment, detection equipment, alarm equipment [and water supply]. Alarm and
detection equipment shall interface to requirements of Electronic Systems. This information shall be
contained in the fire protection design analysis.
S
ection 01012 - Page 11