UFC 4-721-11.1, UEPH Complexes, 26 Nov 01
11.2.9 Electrical and Mechanical Systems: Provide all information as required on the 100% design
submittal developed to 50% completion.
11.2.10 Specifications: Draft of specifications for housing units, including index and trade sections.
11.3
The Final Design - 100% Building Submittal shall contain, as a minimum, the following items
for all submittals:
11.3.1 General: A complete set of construction documents plans and specifications at the same level
of detail as if the project were to be bid including a complete list of equipment, fixtures and materials to
be used. The final drawings are an extension of the reviewed 50% drawings and are to include the
50% comments and responses. All details shall be shown on the drawings.
11.3.2 The design analysis is an extension of the reviewed 50% design analysis and supports and
verifies that the design complies with the requirements of the project.
11.3.3 Submit marked-up specifications. The specifications shall be coordinated with the drawings
and describe in detail all items shown on the drawings.
11.3.4 Landscape, Planting and Turfing Final design drawing(s) shall include a complete schedule of
plant materials which indicates their botanical and common names, plan symbols, quantities, sizes,
condition furnished, and pertinent remarks. Scale of drawing shall be prepared at 1" = 30'. Drawing
shall correspond with the site layout and grading plans and reference coordinates, north arrows,
graphic scales and appropriate legends. An overall planting layout shall be developed and shall
include enlarged detail plans of specific areas as needed, to clarify requirements. Final design
drawings, indicating proposed plants by a (+) mark for the plant location and a circle which is scaled at
approximately 2/3 the ultimate growth spread (diameter) of plants, shall also include a complete
schedule of plant materials which indicates botanical and common names, plan symbols, quantities,
sizes, condition furnished, and pertinent remarks. Final drawings shall also include the basic details
for installation of tree, shrub, and ground cover planting, as well as any other applicable details for
clarification of specific project requirements.
11.3.5 Architectural
11.3.5.1 All architectural drawings shall be coordinated with the other engineering disciplines. Ensure
that the plans are in compliance with the applicable codes. It will be the Contractor's responsibility to
implement the comments generated from any design review submittal as well as verify the consistency
between plans and specification. The evaluation of the Contractor's submittals shall be based on
degree to which the submittal meet the requirements set forth in this document and the specifications.
11.3.5.2 Prewired workstation composite floor plans. Prewired workstation typicals - elevations and
component inventory. Prewired workstation panel identification plan with electrical outlet placement
including base feed.
11.3.5.3 SID package.
11.3.5.4 Fire Protection and Life Safety Analysis. This analysis must be performed by a Registered
Fire Protection Engineer (FPE). NICET certification is not sufficient to address this requirement.
11.3.6 Structural Design
11.3.6.1 Furnish complete checked calculations for all structural members. Incorporate any changes
required by comments on 50% Design Submittal.
11.3.6.2 Prior to this submittal, structural drawings shall be coordinated with all other design
disciplines.