Project Name
Project No. ___________
UFC 4-721-11.1, UEPH Complexes, 26 Nov 01
11.2.6.4 Prepare a plan for each floor of each building that presents a compendium of the total fire
protection features being incorporated into the design. Provide the following types of information:
The location and rating of any fire-resistive construction such as occupancy separations, area
separations, exterior walls, shaft enclosures, corridors, stair enclosures, exit passageways,
etc.
The location and coverage of any fire detection systems.
The location and coverage of any fire suppression systems (sprinkler risers, standpipes, etc.).
The location of any other major fire protection equipment.
Indicate any hazardous areas and their classification.
1
1.2.6.5 Prepare a schedule describing the internal systems with the following information: fire hazard
and occupancy classifications, building construction type, GPM/square foot sprinkler density, area of
operation and other as required.
11.2.6.6 Hydraulic calculations based on water flow test shall be prepared for each sprinkler system
to insure that flow and pressure requirements can be met with current water supply. Include copies of
contractor water flow testing done to certify the available water source.
11.2.7.1 A list of criteria codes, documents and design conditions used. Reference to any authorized
waiver of these criteria or codes.
11.2.7.2 Permits and Registration: Provide a list of all required permits and registrations for
construction of items of special mechanical systems and equipment.
11.2.7.3 A description of the proposed control system.
11.2.7.4 Description, approximate capacity and location of any special mechanical equipment such as
11.2.8 Electronic Systems: Electronic Systems responsibilities include the following:
Fire Detection and Alarm System
Fire Suppression System Control
Public Address System
Telephone System
Cable Television System
Special Grounding Systems
Cathodic Protection
Intrusion Detection, Card Access System
Central Control and Monitoring System
11.2.8.1 The design analysis shall include all calculations required to support design decisions and
estimates at this stage of design. The analysis shall include specific criteria furnished, conference
minutes and cost analyses of all systems considered.
11.2.8.2 Design of the fire alarm and detection system shall include layout drawings for all devices
and a riser diagram showing the control panel, annunciator panel, all zones, radio transmitter and
interfaces to other systems (HVAC, sprinkler, etc.).
S
ection 01012 - Page 12