Loading dock shall be cast-in-place concrete; dock floor shall be [____ mm] below warehouse
floor. Provide resilient dock bumpers at full length of dock. [Provide adjustable dock leveler at
each loading dock door. Provide dock sealing system around each loading dock door. Provide
trailer restraint at each loading dock door.] [User may request to divide the warehouse area
with wire mesh partitions].
2-2.3.2
DX/TS (Direct Exchange/Technical Support). Provide one DX/TS Area per
Warehouse Area; total net area shall be [____] m2. Total occupants: [__]. [Refer to FPS for
authorized area requirements]. At each DX/TS Area provide one 3000 mm wide x 2900 mm
high overhead door opening to hardstand vehicle access surrounding the building. Provide
daylighting through use of metal windows or translucent wall panels at exterior wall area above
overhead door level. [Occupants will use [insert vehicle type, method of propulsion, load rating,
wheel type, reach height] to store and retrieve items from storage shelving within the space.]
Provide wire mesh partitions with sliding doors between DX/TS and Warehouse Area and
Supply/Admin Area.
2-2.3.2.1 Function: Area for turn-in and issue of direct exchange components; storage of items
for Technical Supply function. Storage of [insert types of materials; include hazard/flammability
classifications, methods of storage, height of racks or shelves, and other data the offeror will
need to establish applicable code requirements].
2-2.3.2.2 Adjacency requirements: Adjacent to Warehouse Area and Supply/Admin Area.
Adjacent to hardstand vehicle access aisles.
2-2.3.2.3 Furnishings/Fixtures/Equipment: [Provide, and] design space to accommodate the
following storage systems: [insert types, quantities, dimensions, and load capacities of shelving,
racks, bins, etc. Coordinate with user. Storage systems can be included in the construction
contract ]. Minimum clear aisle width between storage units shall be [3000 mm] [verify with
user]. Provide plastic laminate base cabinets with 14 gauge seamless stainless steel countertop
for the direct exchange process. [Provide wire mesh pass-through window between this room
and Warehouse Area; size pass-through window to accommodate transfer of [insert size of
biggest item; or give desired window size]. Partitions between this space and the core areas
shall be concrete masonry or concrete.
Floor: concrete slab with sealer-hardener
Base: none
Interior side of exterior walls: painted concrete masonry units or painted concrete to overhead
door head height; prefinished metal liner panels above [CMU is recommended for durability. If
required due to budget constraints, metal liner panels may be used full height of interior face of
exterior walls; this also may be considered as an optional bid item]. Exposed structure shall be
painted.
Ceiling: prefinished metal liner panels on underside of roof purlins; exposed structure shall be
painted.
2-2.3.2.5 Other requirements: Provide 300 mm diameter x 1400 mm high, concrete-filled,
schedule 80 galvanized steel, pipe bollards inside the bay at each overhead door jamb (refer to
Chapter 3 for exterior pipe bollards). Provide similar bollards at interior locations as required to
protect structural columns and other elements from damage.
2-2.3.3
Supply/Admin. Provide one Supply/Admin Area per Warehouse Area; total net area
SOW-33