shall be [____] m . Total occupants: [__]. [Refer to FPS for authorized area requirements].
Provide daylighting through use of metal windows or translucent wall panels at exterior wall area
above overhead door level. [Occupants will use [insert vehicle type, method of propulsion, load
rating, wheel type, reach height] to store and retrieve items from storage shelving within the
space.] Provide wire mesh partitions with sliding doors between Supply/Admin Area and DX/TS
and Warehouse Area.
2-2.3.3.1 Function: Workspace for Supply Administration, Warehouse Stock Control and
Accounting personnel. [Add any other functions to be accommodated in the space.] [and
storage of [___]. [Insert types of materials; include hazard/flammability classifications, methods
of storage, height of racks or shelves, and other data the offeror will need to establish applicable
code requirements].
2-2.3.3.2 Adjacency requirements: Adjacent to DX/TS Area, Warehouse Area, and core areas
2-2.3.3.3 Furnishings/Fixtures/Equipment: Design the space to accommodate the following
government provided furniture and equipment [list everything the user will have in the space,
including copiers, fax machine, file cabinets, bookcases, storage units, non-wired office
partitions, etc.; include sizes.]. [Provide, and] design space to accommodate [__] administrative
systems furniture workstations. Refer to Chapter 5 for systems furniture requirements.
[Coordinate with user. Furniture systems are personal property fixed (PPF); they are not MCA
funded, but can be provided as part of construction contract when funded by the user, and
identified as a line item on form DD 1391. If not included in the construction contract, systems
furniture requirements should still be included in Chapter 5 so the offeror will know what to
design the space to accommodate.]. Minimum clear aisle widths shall comply with applicable
codes. [Provide, and] design space to accommodate the following storage systems: [insert
types, quantities, dimensions, and load capacities of shelving, racks, bins, etc. Coordinate with
user. Storage systems can be included in the construction contract ]. Minimum clear aisle width
between storage units shall be [____ mm] [verify with user].
Floor: concrete slab with sealer-hardener
Base: none
Interior side of exterior walls: painted concrete masonry units or painted concrete to overhead
door head height; prefinished metal liner panels above [CMU is recommended for durability. If
required due to budget constraints, metal liner panels may be used full height of interior face of
exterior walls; this also may be considered as an optional bid item]. Exposed structure shall be
painted.
Ceiling: prefinished metal liner panels on underside of roof purlins; exposed structure shall be
painted.
2-2.3.3.5 Other requirements: [
].
2-2.4
Outside Hardstand Areas. Refer to paragraph 3-10 for additional criteria.
2-2.4.1
Waste Oil Storage Tank(s). Provide one above-ground [underground] [___] liter
capacity waste engine oil storage tank per each wing of Repair Bays. Tank shall be constructed
of non-corrosive material. Provide secondary containment in compliance with [applicable state
environmental regulations]. Tank fill shall be accessible by workers, using mobile waste oil
drain receptacles [with pumping capabilities] [with gravity drain valves], without the need to
climb stairs. Tank construction and location shall comply with IBC and NFPA code
requirements. Provide 300 mm diameter x 1400 mm high, concrete-filled, schedule 80