UFC 4-721-11.1, UEPH Complexes, 26 Nov 01
SECTION 01012
DESIGN AFTER AWARD
[Design Districts shall review and edit this specification as necessary to suit the project.]
1.0
GENERAL
1.1 The Contractor shall propose a schedule for the number and composition of the design submittal
phases. As a minimum, design submittals are required at the preliminary (50%), final (100%), and at
the design complete stage. The requirements of each design stage are listed hereinafter. The
Contractor shall reflect the number and schedules for the design submittals phases in the progress
charts. As a maximum, the 50%, 100%, and design complete submittals shall be made in one
consolidated package which includes each of the major categories listed in paragraph "Contents of
Design Submittals".
[Design District shall edit and remove the following paragraph if fast track design-construction is not be
permitted in the particular project. Fast-track design-construction is the established standard for this
program. Designers are cautioned that removal of the fast track option will inherently increase
contractor costs and may cause the proposers to eliminate some quality features from the design
proposal.]
1.2 To facilitate fast-track design-construction activities the contractor shall submit a 100% Site/Utility
Design as the first design submittal. Following review, resolution, and incorporation of all Government
comments, and submittal of a satisfactory set of site/utility design documents, the [insert USACE
Construction District] shall issue a limited Notice to Proceed (NTP) which shall allow the contractor to
proceed with site development activities within the parameters set forth in the accepted design
submittal. Submittal review, comment, and resolution times from this specification apply to this initial
100% Site/Utility Design Submittal. No on-site construction activities shall begin prior to receipt of a
construction NTP by the contractor.
2.0
DESIGNER OF RECORD
The Contractor shall identify, for approval, the Designer of Record for each area of work. One
Designer of Record may be responsible for more than one area. All areas of design disciplines shall
be accounted for by a listed, registered Designer of Record. The Designer(s) of Record shall stamp,
sign, and date all design drawings under their responsible discipline at each design submittal stage
(see SCR - "Registration of Designers" ).
3.0 DEFINITION OF DESIGN SUBMITTALS
3.1
First Site/Utility Design Submittal (100%). This submittal is provided to allow the contractor to
concentrate initial efforts for the site/utility portions of the project. By allowing this work to be
separated, the contractor is given the opportunity to fast track and begin construction on the site/utility
work prior to completion of the building designs. This submittal shall consist of the following:
3.1.1
Design analysis, developed to 100%, site work and utility work only.
3.1.2
100% complete site/utility drawings
3.1.3 Final site/utility specifications
3.1.4 Environmental permits, as required. When environmental permits are not required, the
Contractor shall provide a statement with justification to that effect.
S
ection 01012 - Page 1