Preliminary Conformance 50% Building Submittal. This submittal is intended to insure that
the contractors design is proceeding in accordance with the terms of the solicitation and the
contractor's original proposal as well as in a timely manner. This submittal shall consist of the
following:
3.2.1
Design analysis, developed to 50%
3.2.2
50% complete drawings
3.2.3 Draft specifications
3.2.4 Site Utility design information need not be included in this submittal package except where
interface to the interior building systems is required.
3.3
Final Design - 100% Building. The review of this submittal is to insure that the design is in
accordance with directions provided the Contractor during the design process as well as the original
solicitation and the contractor's proposal. The Contractor shall submit the following documents for
Final Design Review:
3.3.1 50% review comments and responses.
3.3.2 The Design Analysis submitted for Final Design Review shall be in its final form. The Design
Analysis shall include all backup material previously submitted and revised as necessary. All design
calculations shall be included. The Design Analysis shall contain all explanatory material giving the
design rationale for any design decisions which would not be obvious to an engineer reviewing the
Final Drawings and Specifications.
3.3.3 The Contract Drawings submitted for Final Design Review shall include the drawings previously
submitted which have been revised and completed as necessary. The Contractor is expected to have
completed all of his coordination checks and have the drawings in a design complete condition. The
drawings shall be complete at this time including the incorporation of any design review comments
generated by the previous design reviews. The drawings shall contain all the details necessary to
assure a clear understanding of the work throughout construction. Shop drawings will not be
considered as design drawings. All design shall be shown on design drawings prior to submittal of
shop drawings.
3.3.4 The Draft Specifications on all items of work submitted for Final Design Review shall consist of
legible marked-up specification sections.
3.3.5 Site Utility design information need not be included in this submittal package except where
interface to the interior building systems is required.
3.4
Design Complete Submittal. After the Final Design Review, the Contractor shall revise the
Contract Documents by incorporating any comments generated during the Final Design Review and
shall prepare final hard copy Contract Specifications. The Contractor shall submit the following
documents for the design complete submittal:
3.4.1 Design analysis, in final 100% complete form.
3.4.2 100% complete drawings.
3.4.3 Final specifications
3.4.4 Final review comments and responses.
S