Project Name
Project No. ___________
UFC 4-214-02, TEMF, 24 Jul 03
Type system recommended, comparison of systems, cost estimates showing all equipment
alternatives.
Calculations on all systems that are considered showing all information and descriptions.
11.2.8.7.1 Design of Cathodic Protection. The design shall clearly provide a thorough and
comprehensive specification and drawing. The design plans and specifications shall show extent of
the facilities to be protected, location and type of anodes, location of test points, details for
sectionalizing an underground piping system. This design shall be complete enough to purchase
equipment and build without design changes to meet criteria of protection.
11.2.8.8 Exterior work to be shown on electrical site plan.
Existing and new communications service lines, both overhead and underground, shall be
properly identified.
Show removals and relocations, if any.
11.2.8.9 Provide a descriptive narrative of all electronic systems that are required for project. Define
any hazardous areas (as defined in the National Electric Code) and indicate the type of equipment
proposed for use in such areas. Show the location of all electronic system panels, etc., on the floor
plans. Show the proposed riser diagrams for all systems. Sizes of all conduit, wires, cables, panels,
etc. Provide a complete symbol legend for all devices or equipment shown on the plans. For work
requiring removals or demolition, the designer shall show by use of drawings or narrative, how
demolition work is to be done.
11.2.9 Electrical and Mechanical Systems: Provide all information as required on the 100% design
submittal developed to 50% completion.
11.2.10 Specifications: Draft of specifications for all facilities, including index and trade sections.
11.3
The Final Design - 100% Building submittal shall contain, as a minimum, the following items
for all submittals:
11.3.1 General: A complete set of construction documents plans and specifications at the same level
of detail as if the project were to be bid including a complete list of equipment, fixtures and materials to
be used. The final drawings are an extension of the reviewed 50% drawings and are to include the
50% comments and responses. All details shall be shown on the drawings.
11.3.2 The design analysis is an extension of the reviewed 50% design analysis and supports and
verifies that the design complies with the requirements of the project.
11.3.3 Submit marked-up specifications. The specifications shall be coordinated with the drawings
and describe in detail all items shown on the drawings.
11.3.4 Not Used.
11.3.5 Architectural
11.3.5.1 All architectural drawings shall be coordinated with the other engineering disciplines. Ensure
that the plans are in compliance with the applicable codes. It will be the Contractor's responsibility to
implement the comments generated from any design review submittal as well as verify the consistency
between plans and specification. The evaluation of the Contractor's submittals shall be based on
degree to which the submittal meet the requirements set forth in this document and the specifications.
11.3.5.2 Prewired workstation composite floor plans. Prewired workstation typicals - elevations and
Section 01012 - Page 13