Project Name
Project Number
TEMF
Statement of Work
UFC 4-214-02, 24 Jul 03
remove engine exhaust from vestibule area. Provide vehicle exhaust evacuation system to
allow [__] running vehicles to be simultaneously connected.]
Floor: epoxy coating on concrete slab
Base: none
Exterior walls: exposed concrete masonry units or exposed concrete to vehicle door height;
prefinished metal liner panels above. Exposed structure shall be painted.
Ceiling: prefinished metal liner panels on underside of roof purlins; exposed structure shall be
painted. Clear ceiling height shall not be lower than vehicle door height.].
2-2.1.8.5 Other requirements: Provide 300 mm diameter x 1400 mm high, concrete-filled,
schedule 80 galvanized steel, pipe bollards inside the bay at each vehicle door jamb (refer to
Chapter 3 for exterior pipe bollards).
2-2.1.9
[Inside POL Storage. Provide heated indoor storage area for petroleum oils and
lubricants used in the repair and scheduled maintenance bays.; net area [____] m2 [Include
paragraph only if project is in weather region 1-4.] .
2-2.1.9.1 [Function: Heated area for POL storage, with direct access to repair and scheduled
maintenance bays]
2-2.1.9.2 [Adjacency requirements: Adjacent to repair bays and/or scheduled maintenance
bay(s). ]
2-2.1.9.3 [Furnishings/Fixtures/Equipment:]
Floor: epoxy coating on concrete slab
Base: none
Exterior walls: painted concrete masonry units or exposed concrete to vehicle door height;
prefinished metal liner panels above. Exposed structure shall be painted.
Ceiling: prefinished metal liner panels on underside of roof purlins; exposed structure shall be
painted. Clear ceiling height shall not be lower than vehicle door height.].
2-2.1.9.5
[Other requirements:]
2-2.2
Core Areas. Each maintenance building will contain a core area to accommodate
admin and shop control, general item repair, [compact item repair,] [special environment repair,]
tool room(s), tool box storage, repairable exchange/technical supply, PLL,
break/training/conference room, weapons/COMSEC vault(s), latrine/shower/locker rooms, and
non-assignable/utility spaces. Core areas may be arranged in one or two story configurations.
The core area, with accompanying repair bays [and warehouse bays], will constitute the primary
building component for Army tactical equipment maintenance facilities. Other site storage
building requirements (POL storage building and deployment storage building) are covered in
Chapter 3. [The core area will be sized to accommodate the occupying unit's TOE/TDA, subject
to the limitations of FPS, the TEMF Standard Design, and the information provided in the
following paragraphs. The core area components, adjacencies, and sizes are subject to the
limitations indicated in the TEMF Standard Design (seven standard core sizes].
2-2.2.1
Admin and Shop Control. Provide one space per core; minimum total net area