Project Name
Project Number
TEMF
Statement of Work
UFC 4-214-02, 24 Jul 03
are located on both sides of a core, each side of core shall have a Tool Room). Locate on first
floor; minimum total net area of all Tool Rooms shall be [____] m2 . Total occupants: [__] [In
TDA facilities space is authorized at 9 m2 net area per each tool room keeper; In TOE's space is
authorized at 9 m2 net area per each unit common tool kit assigned to the organization, and 4
m2 net area per each supplemental tool kit assigned to the unit]. Provide personnel door
between Tool Room and Circulation Bay. Walls or partitions between this space and other
spaces shall be concrete masonry or concrete. Partition between this space and Tool Box
Storage shall be wire mesh.
2-2.2.2.1 Function: Issue and secure storage of common tool kits shared by shop personnel.
2-2.2.2.2 Adjacency requirements: Adjacent to Circulation Bay and Tool Box Storage.
2-2.2.2.3 Furnishings/Fixtures/Equipment: Design the space to accommodate the following
government provided furniture and equipment [list everything the user will have in the space;
include sizes.]. [Provide, and design space to accommodate the following tool storage systems:
_____] [Coordinate with user. If not provided by the activity, list required storage shelving,
racks, cabinets, etc].
Floor: epoxy coating on concrete slab
Base: [none] [resilient, if gypsum board partitions used]
Walls: painted concrete masonry units. Exposed structure shall be painted.
Ceiling: exposed structure, painted.
2-2.2.2.5 Other requirements: [
].
2-2.2.3
Tool Box Storage. Provide one Tool Box Storage Room for each wing of Repair
Bays (if Repair Bays are located on both sides of a core, each side of core shall have a Tool
Box Storage Room). Locate on first floor; minimum total net area of all Tool Box Storage
Rooms shall be [____] m2 . Total occupants: [__] [Space is authorized at .3 m2 net area per
each person working inside the shop; and 2 m2 net area per each person working outside the
shop (members of contact teams)]. Provide personnel door between Tool Box Storage Room
and Circulation Bay. Walls or partitions between this space and other spaces shall be concrete
masonry or concrete. Partition between this space and Tool Room shall be wire mesh.
2-2.2.3.1 Function: Issue and secure storage of tool kits used by shop personnel.
2-2.2.3.2 Adjacency requirements: Adjacent to Circulation Bay and Tool Room.
2-2.2.3.3 Furnishings/Fixtures/Equipment: Design the space to accommodate the following
government provided furniture and equipment [list everything the user will have in the space;
include sizes.]. [Provide, and design space to accommodate the following tool storage systems:
_____] [Coordinate with user. If not provided by the activity, list required storage shelving,
racks, cabinets, etc].
Floor: epoxy coating on concrete slab
Base: [none] [resilient, if gypsum board partitions used]
Walls: painted concrete masonry units. Exposed structure shall be painted.
Ceiling: exposed structure, painted.
SOW-18